Beam Concrete Calculator

Beam concrete = span × width × depth. Measure only the part below the slab if the slab is measured separately: a 300 × 600 mm beam under a 150 mm slab counts 450 mm deep, so a 6 m beam is 0.81 m³. Six of them need 4.86 m³ (5.10 m³ with 5%).

Free Account Required

Sign up free with your email or Google to use this calculator. It takes under a minute and unlocks every calculator on the site.

Behind this panel: an example with the default sizes.

Inputs

Results update as you type.

Beams
m
mm
mm
mm
Supply
%
Beam section300 mm600 mm150 mmSection · span 6 m × 6shaded = countedmyconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Beam concrete to order
5.10m³
Per beam0.810 m³
Depth counted450 mm
Order (rounded to 0.5 m³)5.50 m³
Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Depth below slab = 0.600 − 0.150 = 0.450 m
  2. Per beam = span × b × d = 6.000 × 0.300 × 0.450 = 0.810
  3. × 6 = 4.860; + 5% = 5.10

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formulas

Depth counted  = D − t_slab   (below slab)   or   D   (full depth)
Volume         = span × b × depth counted × n

Worked example

Six beams 300 × 600 mm, 6 m clear span, 150 mm slab, below-slab only:

  1. Depth = 600 − 150 = 450 mm
  2. Per beam = 6 × 0.3 × 0.45 = 0.81 m³
  3. Total = 4.86 m³; with 5% = 5.10 m³

Concrete per metre of beam

Beam b × D Full depth Below a 150 mm slab
230 × 450 mm 0.104 m³ 0.069 m³
300 × 600 mm 0.180 m³ 0.135 m³
300 × 750 mm 0.225 m³ 0.180 m³
400 × 900 mm 0.360 m³ 0.300 m³

Frequently Asked Questions

How do I calculate beam concrete?

Multiply the clear span by the beam width and depth. If the slab is poured with the beam and measured as a full slab, count only the depth below the slab to avoid double counting.

Should I use clear span or centre-to-centre length?

Clear span between column faces, when columns are measured to the underside of the beam. Use centre-to-centre only if columns stop at the slab soffit in your take-off method.

How much concrete per metre of beam?

Width × depth. A 300 × 600 mm beam is 0.18 m³ per metre full depth, or 0.135 m³ per metre below a 150 mm slab.

All Concrete Calculators