Concrete Curing Schedule Generator

A curing schedule lists what happens each day from the pour: start curing as soon as the surface won't mark, strike side forms at about 24 hours, keep the concrete wet every day of the curing period (7 days for normal cement), strike soffits when strength allows, and test cubes at 7 and 28 days.

Free Account Required

Sign up free with your email or Google to use this calculator. It takes under a minute and unlocks every calculator on the site.

Behind this panel: an example with the default sizes.

Inputs

Results update as you type.

Pour
°C
Curing
Formwork
Curing 7 daysCuring 7 dayskeep wet01371428daysstrike sidessoffits7-day test28-day testmyconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Curing ends
Mon, 9 Nov 2026(7 days)
Day 0: Mon, 2 Nov 2026Pour and finish; start wet hessian / burlap kept damp as soon as the surface will not mark
Day 1: Tue, 3 Nov 2026Strike side forms (24 h); cure the exposed faces straight away
Day 1: Tue, 3 Nov 2026Re-wet 3× and check covers
Day 2: Wed, 4 Nov 2026Re-wet 3× and check covers
Day 3: Thu, 5 Nov 2026Re-wet 3× and check covers
Day 4: Fri, 6 Nov 2026Re-wet 3× and check covers
Day 5: Sat, 7 Nov 2026Re-wet 3× and check covers
Day 5: Sat, 7 Nov 2026Soffit forms / props may be struck at ~70% if the engineer agrees (backprop as specified)
Day 6: Sun, 8 Nov 2026Re-wet 3× and check covers
Day 7: Mon, 9 Nov 2026Last day of curing: remove covers gradually to avoid thermal shock
Day 7: Mon, 9 Nov 2026Test 7-day cubes / cylinders
Day 28: Mon, 30 Nov 2026Test 28-day cubes / cylinders

Striking times are estimates: confirm with field-cured specimens or maturity sensors and the temporary works engineer.

Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Soffit striking day from EN 1992-1-1 strength gain (class N, 20 °C average): 70% at day 5
  2. Use the Print button to post the schedule on site
Site Reminders

Get a notification on this phone on the day. Tick the dates you want, then tap Remind me.

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

How the Schedule Is Built

Day 0           pour, finish, start curing
Side forms      after the hours you set (often 24 h)
Days 1 … N      re-wet or inspect, according to the method
Soffit striking day the strength model reaches your striking %
Day N           end curing; remove covers gradually
Days 7 and 28   test specimens

Worked Example

Wet hessian, class N cement, 20 °C, 7-day curing, 3 re-wetting rounds a day, side forms at 24 h, soffits at 70%, poured Monday 2 November 2026:

Day Date Action
0 Mon 2 Nov Pour, finish, start wet hessian
1 Tue 3 Nov Strike side forms; re-wet 3×
2–4 Wed–Fri Re-wet 3× a day
5 Sat 7 Nov Soffit striking at ~70% if the engineer agrees
7 Mon 9 Nov End of curing; 7-day cube tests
28 Mon 30 Nov 28-day cube tests

Frequently Asked Questions

How often should concrete be watered during curing?

Often enough that the surface never dries, typically several times a day under wet hessian, more in hot, dry or windy weather. Ponding and sheeting need less frequent attention.

When should curing start?

As soon as the surface can take it without damage, usually right after finishing, once the bleed water has gone. Curing compound is sprayed at that point too.

Can I stop curing early if the concrete looks hard?

No. Surface hardness is not a sign of adequate curing. Stopping early weakens and dusts the surface and increases cracking.

References

  • ACI 308.1 (Specification for Curing Concrete); EN 1992-1-1 strength development