Dry volume of mortar = wet volume × 1.33. For 1 m³ of 1:6 cement mortar the dry volume is 1.33 m³, which splits into 0.19 m³ of cement (5.47 bags of 50 kg) and 1.14 m³ of sand.

Free Account Required

Sign up free with your email or Google to use this calculator. It takes under a minute and unlocks every calculator on the site.

Behind this panel: an example with the default sizes.

Inputs

Results update as you type.

Mortar
m³
Factors
Mortar 1:6Mortar 1:61Cement: 5.47 bags6Sand: 1.14 m³myconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Cement (50 kg bags)
5.47bags
Sand1.14 m³
Cement weight274 kg
Water (approx.)137 L
Bags to buy6 bags
Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Dry volume = 1.000 × 1.33 = 1.330 m³
  2. Cement = 1.330 ÷ (1 + 6) = 0.190 m³ → ÷ 0.0347 m³ per bag = 5.47 bags
  3. Sand = 1.330 × 6 ÷ 7 = 1.140 m³
  4. Water = cement weight × 0.50

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formula

Dry volume = wet volume × 1.33
Cement     = dry volume ÷ (1 + sand parts)        → × 1,440 kg/m³ ÷ 50 kg = bags
Sand       = dry volume × sand parts ÷ (1 + sand parts)

Worked Example

1 m³ of 1:6 cement mortar:

  1. Dry volume = 1 × 1.33 = 1.33 m³
  2. Cement = 1.33 ÷ 7 = 0.19 m³ × 1,440 = 273.6 kg = 5.47 bags
  3. Sand = 1.33 × 6 ÷ 7 = 1.14 m³

Cement and Sand per m³ of Mortar

Dry volume factor 1.33, 50 kg bags.

Mix Cement Sand
1:3 9.58 bags 1.00 m³
1:4 7.66 bags 1.06 m³
1:5 6.38 bags 1.11 m³
1:6 5.47 bags 1.14 m³

More Dry Volumes

Frequently Asked Questions

Why is 1.33 used for the dry volume of mortar?

Dry sand and cement contain air gaps, and sand also bulks when damp. Once water is added and the mortar is mixed, the cement fills the gaps between sand grains, so the wet mortar takes up less space. About 33% more dry material is needed, hence 1.33. Some estimators use 1.27 to 1.35.

Is the 1.33 factor given in an IS code?

No. It is an estimating convention from site practice and textbooks, not a clause of IS 456 or IS 2250. Use your own site's figure if you have measured it.

Why is mortar's factor smaller than concrete's 1.54?

Concrete has coarse aggregate with large gaps that the sand and cement fill, so its dry materials shrink more when mixed. Mortar has only sand and cement, so the reduction is smaller.