Dry volume of mortar = wet volume × 1.33. For 1 m³ of 1:6 cement mortar the dry volume is 1.33 m³, which splits into 0.19 m³ of cement (5.47 bags of 50 kg) and 1.14 m³ of sand.
Free Account Required
Sign up free with your email or Google to use this calculator. It takes under a minute and unlocks every calculator on the site.
Cement = 1.330 ÷ (1 + 6) = 0.190 m³ → ÷ 0.0347 m³ per bag = 5.47 bags
Sand = 1.330 × 6 ÷ 7 = 1.140 m³
Water = cement weight × 0.50
Scan to open this calculationThe code links to this calculator with your inputs, so anyone can scan it with a phone camera and see the same result. Save it for a report, a site board or WhatsApp.Test copy: this code opens the live site, myconstructioncalculator.com, so it works on a phone once the site is launched.
Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.
Dry sand and cement contain air gaps, and sand also bulks when damp. Once water is added and the mortar is mixed, the cement fills the gaps between sand grains, so the wet mortar takes up less space. About 33% more dry material is needed, hence 1.33. Some estimators use 1.27 to 1.35.
Is the 1.33 factor given in an IS code?
No. It is an estimating convention from site practice and textbooks, not a clause of IS 456 or IS 2250. Use your own site's figure if you have measured it.
Why is mortar's factor smaller than concrete's 1.54?
Concrete has coarse aggregate with large gaps that the sand and cement fill, so its dry materials shrink more when mixed. Mortar has only sand and cement, so the reduction is smaller.