Construction Duration Calculator

Each activity takes quantity ÷ (output per crew-day × crews). 400 m³ of excavation (5 days), 120 m³ of concrete (6), 600 m² of blockwork with 2 crews (12) and 1,200 m² of plaster with 2 crews (15) add up to 38 days: 42 working days with a 10% allowance, finishing about 7 weeks later on a Monday–Saturday week.

Free Account Required

Sign up free with your email or Google to use this calculator. It takes under a minute and unlocks every calculator on the site.

Behind this panel: an example with the default sizes.

Inputs

Results update as you type.

Activity 1 (e.g. Excavation (m³))
Activity 2 (e.g. Concrete (m³))
Activity 3 (e.g. Blockwork (m²))
Activity 4 (e.g. Plaster (m²))
Activity 5 (optional)
Calendar
Activity scheduleDuration 42 working days ≈ 6.9 weeksActivity 1Activity 2Activity 3Activity 4myconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Estimated duration
42 working days≈ 6.9 weeks
Estimated finishSat, 19 Dec 2026
Activity 15.0 days 400 ÷ (80 × 1 crew)
Activity 26.0 days 120 ÷ (20 × 1 crew)
Activity 312.0 days 600 ÷ (25 × 2 crews)
Activity 415.0 days 1,200 ÷ (40 × 2 crews)

A first estimate only. A programme with real dependencies, resources and approvals (critical path) gives the reliable date.

Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Days per activity = quantity ÷ (output per crew-day × crews)
  2. Total = first activity + later activities × (1 − 0% overlap), + 10% allowance = 41.8 → 42 working days
  3. Calendar: monday to saturday from Mon, 2 Nov 2026

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formula

Days per activity = quantity ÷ (output per crew-day × crews)
Total             = first + Σ later × (1 − overlap), × (1 + allowance)
Finish            = start + working days on your calendar

Worked Example

Activity Quantity Output / crew-day Crews Days
Excavation 400 m³ 80 1 5
Concrete 120 m³ 20 1 6
Blockwork 600 m² 25 2 12
Plaster 1,200 m² 40 2 15

Total 38 days + 10% = 42 working days (≈ 7 weeks, Monday–Saturday).

Frequently Asked Questions

How do I estimate construction time?

Break the work into activities, estimate the quantity and realistic output of each crew, divide to get days, then add them in sequence (overlapping where trades can work at the same time) and add an allowance for weather and risk.

Where do output rates come from?

Your own past jobs are best. Published norms and supplier data help, but adjust for site access, weather, crew skill and how repetitive the work is.

Is this a project programme?

No: it is a quick estimate. A proper programme maps dependencies, resources, approvals and the critical path.