CONCRETE CURING & POUR PLANNING · FIELD TOOL

Concrete Pour Sequence Planner

Split the slab into bays no larger than one day's pour, then cast alternate bays first and the infill bays after a waiting period. A 40 × 30 m slab, 200 mm thick (240 m³), with 60 m³ a day, becomes four 20 × 15 m bays: A1 and B2 first, then B1 and A2 three days later.

Inputs

Results update as you type.

Slab
m
m
mm
Pours
m³
Pour sequence by bay40 m30 m1432first setinfill (numbers = pour order)myconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Pours needed
4bays of 20.00 × 15.00 m
Volume per bay60.0 m³
Last pourSat, 7 Nov 2026
Pour 1: Mon, 2 Nov 2026Bay A1 first set
Pour 2: Tue, 3 Nov 2026Bay B2 first set
Pour 3: Fri, 6 Nov 2026Bay B1 infill
Pour 4: Sat, 7 Nov 2026Bay A2 infill

Bay sizes and joint positions must match the joint layout on the drawings: check with the engineer before setting out.

Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Total = 40.00 × 30.00 × 0.200 m = 240.0 m³ → at most 60.0 m³ per pour → 2 × 2 bays
  2. Checkerboard: bays where column + row is even go first, so no two fresh bays touch; the infill set starts 3 days after the last first-set pour
  3. Bays are labelled by column letter (A, B, …) along the length and row number across the width

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Method

Bays           = ⌈total volume ÷ maximum daily pour⌉, arranged in columns × rows
First set      = bays where column + row is even (no two touch)
Infill set     = remaining bays, starting the waiting period after the last first-set pour
One bay per pour day, on your chosen working days

Worked Example

40 × 30 m slab, 200 mm thick (240 m³), 60 m³ per day, 3-day wait, Monday–Saturday, starting Monday 2 November 2026:

Pour Date Bay Set
1 Mon 2 Nov A1 First
2 Tue 3 Nov B2 First
3 Fri 6 Nov B1 Infill
4 Sat 7 Nov A2 Infill

Bays are 20 × 15 m, 60 m³ each. Columns are lettered along the length and rows numbered across the width.

Frequently Asked Questions

What is a checkerboard pour sequence?

Casting alternate bays first (like the black squares of a chessboard) and the remaining bays later, so that each new bay is placed against concrete that has already done some of its early shrinkage.

How big should each pour bay be?

No larger than the crew, pump and plant can place and finish in one shift, and arranged so the joints fall where the drawings show construction or movement joints.

How long should I wait before pouring the infill bays?

It depends on the specification: commonly a few days to a week. The calculator lets you set the gap.