Concrete Pour Duration Calculator

Pour duration = volume ÷ the lower of the pump rate and the truck supply rate. 120 m³ with a 40 m³/h pump and six 8 m³ trucks on a 60-minute cycle (48 m³/h supply) takes 3 hours: starting at 07:00, finishing about 10:00, with a truck every 12 minutes.

Inputs

Results update as you type.

Pour
m³
Placing
m³
Supply
m³
Pour timeline with truck arrivalsPour 3 h 00 min · finish 10:0007:0010:00a truck every 12 minmyconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Pour duration
3 h 00 min
Estimated finish10:00
Placing rate achieved40.0 m³/h limited by the pump
Truck supply rate48.0 m³/h
Truck loads15
One truck every12 min
Trucks to keep the pump busy5
Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Supply = trucks × capacity × 60 ÷ cycle = 6 × 8.0 × 60 ÷ 60 = 48.0 m³/h
  2. Placing rate = lower of pump 40.0 m³/h and supply → 40.0 m³/h
  3. Duration = 120.0 m³ ÷ 40.0 m³/h = 3.00 h; finish ≈ 10:00

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formulas

Supply rate      = trucks × truck capacity × 60 ÷ round trip (min)
Placing rate     = min(pump rate, supply rate)
Duration         = volume ÷ placing rate
Truck interval   = capacity ÷ placing rate
Trucks for pump  = pump rate × round trip ÷ (60 × capacity)

Worked Example

120 m³, pump 40 m³/h, six 8 m³ trucks on a 60-minute cycle, first truck at 07:00:

  1. Supply = 6 × 8 × 60 ÷ 60 = 48 m³/h, more than the pump, so the pump governs
  2. Duration = 120 ÷ 40 = 3 h 00 min → finish ≈ 10:00
  3. 15 loads, one every 12 minutes; 5 trucks would just keep the pump busy

Pour Time by Placing Rate

Volume 25 m³/h 40 m³/h 60 m³/h
50 m³ 2.0 h 1.3 h 0.8 h
100 m³ 4.0 h 2.5 h 1.7 h
200 m³ 8.0 h 5.0 h 3.3 h
400 m³ 16.0 h 10.0 h 6.7 h

Frequently Asked Questions

How long does it take to pour concrete?

Divide the volume by the realistic placing rate. Pumps commonly place 25–60 m³ per hour including truck changeovers, but if trucks cannot arrive fast enough, supply sets the pace.

How many trucks do I need for a pour?

Enough to match the pump: pump rate × truck round-trip time ÷ truck capacity. A 40 m³/h pump with 60-minute cycles and 8 m³ trucks needs 5 trucks.

What happens if there is a long gap between trucks?

Concrete already placed starts to set, and a cold joint can form where fresh concrete meets it. Keep intervals short, especially in hot weather, and plan where a construction joint could go if supply fails.