Pour duration = volume ÷ the lower of the pump rate and the truck supply rate. 120 m³ with a 40 m³/h pump and six 8 m³ trucks on a 60-minute cycle (48 m³/h supply) takes 3 hours: starting at 07:00, finishing about 10:00, with a truck every 12 minutes.
My Construction Calculator
Concrete Pour Duration Calculator
Inputs
Results update as you type.
Diagram updates as you type.
Results
Check the working before you order.
Pour duration
3 h 00 min
Estimated finish
10:00
Placing rate achieved
40.0 m³/h limited by the pump
Truck supply rate
48.0 m³/h
Truck loads
15
One truck every
12 min
Trucks to keep the pump busy
5
Price This optional: add your own prices
Your prices are remembered on this device only.
Send Order WhatsApp, SMS or email to your supplier
Scan to open this calculationThe code links to this calculator with your inputs, so anyone can scan it with a phone camera and see the same result. Save it for a report, a site board or WhatsApp.Test copy: this code opens the live site, myconstructioncalculator.com, so it works on a phone once the site is launched.
Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.
120 m³, pump 40 m³/h, six 8 m³ trucks on a 60-minute cycle, first truck at 07:00:
Supply = 6 × 8 × 60 ÷ 60 = 48 m³/h, more than the pump, so the pump governs
Duration = 120 ÷ 40 = 3 h 00 min → finish ≈ 10:00
15 loads, one every 12 minutes; 5 trucks would just keep the pump busy
Pour Time by Placing Rate
Volume
25 m³/h
40 m³/h
60 m³/h
50 m³
2.0 h
1.3 h
0.8 h
100 m³
4.0 h
2.5 h
1.7 h
200 m³
8.0 h
5.0 h
3.3 h
400 m³
16.0 h
10.0 h
6.7 h
Frequently Asked Questions
How long does it take to pour concrete?
Divide the volume by the realistic placing rate. Pumps commonly place 25–60 m³ per hour including truck changeovers, but if trucks cannot arrive fast enough, supply sets the pace.
How many trucks do I need for a pour?
Enough to match the pump: pump rate × truck round-trip time ÷ truck capacity. A 40 m³/h pump with 60-minute cycles and 8 m³ trucks needs 5 trucks.
What happens if there is a long gap between trucks?
Concrete already placed starts to set, and a cold joint can form where fresh concrete meets it. Keep intervals short, especially in hot weather, and plan where a construction joint could go if supply fails.
Embed This Calculator on Your Website
Free for any website: contractors, suppliers, blogs and schools. Paste this code where you want the calculator to appear. It works in WordPress (Custom HTML block), Wix, Squarespace and plain HTML.