CONCRETE · FIELD TOOL

Raft Concrete Calculator

Raft concrete = raft slab + downstand beams + column thickenings. A 20 × 15 m raft 600 mm thick (180 m³) with 70 m of 600 × 400 mm ground beams (16.8 m³) and twelve 2 × 2 × 0.3 m thickenings (14.4 m³) needs 211 m³: 217.5 m³ with 3%, 28 trucks and about 5.4 hours on one pump.

Free Account Required

Sign up free with your email or Google to use this calculator. It takes under a minute and unlocks every calculator on the site.

Behind this panel: an example with the default sizes.

Inputs

Results update as you type.

Raft
m
m
mm
Downstand beams
m
mm
mm
Column thickenings
m
mm
Pour
%
m³
m³
Raft with downstandsRaft section · 20 m × 15 m600 mmbeam 400 mmthickening 300 mmmyconstructioncalculator.comNot to scale
Diagram updates as you type.

Results

Check the working before you order.

Raft concrete to order
217.5m³
Raft slab180.0 m³
Downstand beams16.8 m³
Column thickenings14.4 m³
Pour duration (one pump)5.4 h
Order (rounded to 0.5 m³)218.00 m³
Ready-mix trucks28 trucks (last 2.00 m³)
Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Raft = L × W × t = 180.0; beams = length × b × d = 16.8; thickenings = n × a² × d = 14.4
  2. Total = 211.2; + 3% = 217.5 m³
  3. Duration = 217.5 ÷ 40 per hour = 5.4 h
  4. Trucks = ⌈218.00 ÷ 8.0⌉ = 28

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formulas

Raft          = L × W × t
Beams         = total beam length × width × depth below raft
Thickenings   = n × a × a × depth below raft
Pour time     = order ÷ pump output

Worked Example

A 20 × 15 m raft, 600 mm thick, 70 m of 600 × 400 mm downstand beams, twelve 2 × 2 m thickenings 300 mm deep:

  1. Raft = 180.0 m³; beams = 16.8 m³; thickenings = 14.4 m³
  2. Total = 211.2 m³; with 3% = 217.5 m³
  3. Trucks = ⌈218 ÷ 8⌉ = 28
  4. At 40 m³/h: 5.4 hours

Pour Duration for 217.5 m³

Pump output Duration
30 m³/h 7.3 h
40 m³/h 5.4 h
60 m³/h 3.6 h
80 m³/h (two pumps) 2.7 h

Frequently Asked Questions

How do I calculate concrete for a raft foundation?

Raft length × width × thickness, plus downstand beams (total length × width × depth below the raft) and any local thickenings under columns or lift pits.

How long will a raft pour take?

Divide the order volume by the realistic pump output, often 30–60 m³ per hour per pump including truck changeovers. Large rafts use two pumps or are split by construction joints.

Do thick rafts need special care?

Rafts over about 1 m thick can generate enough heat to crack. Many specifications require a thermal control plan, temperature monitoring and sometimes low-heat mixes.

All Concrete Calculators