Basement Excavation Calculator

Basement excavation = (length + 2 × working space) × (width + 2 × working space) × depth. A 20 × 15 m basement 3.5 m deep with 1 m working space is 22 × 17 × 3.5 = 1,309 m³: 1,636 m³ loose, 164 loads of 10 m³, about 3 days at 60 loads a day.

Inputs

Results update as you type.

Basement
m
m
m
m
Haulage
m³
Basement excavation15 m3.5 mBasement section · working space 1 mmyconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Basement excavation (bank)
1,309m³
Loose volume to haul1,636.25 m³
Truck loads164 loads
Haul duration3 working days
Dig footprint22.00 × 17.00 m
Retained face (shoring / piling area)273 m²

Excavations deeper than about 1.2–1.5 m (4–5 ft) need sloping, benching, shoring or a trench box under most safety rules.

Basement excavations usually need a temporary works design for shoring, dewatering and neighbouring structures.

Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Footprint = (20.00 + 2 × 1.00) × (15.00 + 2 × 1.00) = 22.00 × 17.00 m
  2. Volume = 22.00 × 17.00 × 3.50 = 1,309 m³
  3. Loose = 1,309.00 × (1 + 25%) = 1,636.25 m³; loads = ⌈1,636.25 ÷ 10.0⌉ = 164
  4. Days = ⌈164 loads ÷ 60 per day⌉ = 3

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formulas

Footprint     = (L + 2s) × (W + 2s)
Volume        = footprint × D                   (prismoidal if battered)
Retained face = 2 × ((L + 2s) + (W + 2s)) × D   (vertical sides)
Haul days     = ⌈truck loads ÷ loads per day⌉

Worked example

A basement 20 × 15 m, 3.5 m deep, 1 m working space, shored vertical sides, common earth, 10 m³ trucks, 60 loads a day:

  1. Footprint = 22 × 17 m
  2. Volume = 22 × 17 × 3.5 = 1,309 m³
  3. Loose = 1,309 × 1.25 = 1,636 m³ → 164 loads
  4. Haul time = ⌈164 ÷ 60⌉ = 3 days
  5. Retained face = 2 × (22 + 17) × 3.5 = 273 m²

Haul days for 164 loads

Loads per day Days
40 5
60 3
80 3
100 2

Assumptions

  • Flat existing ground; for sloping sites, use average depths from the bulk excavation calculator.
  • Basements need temporary works design for support, dewatering and nearby structures.

Frequently Asked Questions

How much soil comes out of a basement?

Multiply the dig footprint (basement plus working space) by the depth to the underside of the blinding. Then add 20–40% for swell to get the loose volume you will haul away.

How much working space does a basement need?

Often 0.6–1.0 m around the walls for formwork, waterproofing and drainage. With shoring and blind-side waterproofing it can be close to zero.

What is the retained face area?

The perimeter of the dig × its depth: the area of sheet piles, secant piles or soldier piles needed when the sides are vertical.