Temporary Access Road Planner

A 200 m site road 4 m wide with 300 mm of compacted stone, a passing bay and a 100 m² turning head covers 930 m². It needs 279 m³ compacted (349 m³ loose), about 586 t of stone at 2,100 kg/m³ or 30 loads of 20 t, and about 1,240 m² of geotextile.

Inputs

Results update as you type.

Road
m
m
mm
Passing & turning
m
m²
m²
Materials
kg/m³
m
t
Access road plan586 t · 30 loads200 m4 m wide · 300 mm stonemyconstructioncalculator.comNot to scale
Diagram updates as you type.

Results

Check the working before you order.

Crushed stone
586t
Compacted volume279 m³
Loose volume to deliver349 m³
Geotextile1,243 m²
Road area incl. bays and turning930 m²
Passing bays1
Tipper loads30

Thickness depends on ground strength (CBR) and traffic: check with the temporary works designer, and plan drainage ditches alongside.

Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Area = 200 × 4.0 + 1 bays × 30 + 100 m² = 930 m²
  2. Compacted = area × 300 mm = 279 m³; tonnes = × 2,100 kg/m³ = 586 t
  3. Geotextile = road length × (width + 2 × 0.50 m) + bays + turning, + 10% laps

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formulas

Area      = length × width + passing bays + turning area
Stone     = area × compacted thickness  (× loose factor to order by volume)
Tonnes    = compacted volume × density
Geotextile = length × (width + 2 × edge extra) + bays + turning, + laps

Worked Example

200 m × 4 m, 300 mm, 1 passing bay of 30 m² (one every 100 m), 100 m² turning head:

  1. Area = 800 + 30 + 100 = 930 m²
  2. Compacted = 279 m³ → loose 349 m³; 586 t
  3. Geotextile ≈ 1,243 m²; 30 tipper loads of 20 t

Frequently Asked Questions

How thick should a temporary haul road be?

It depends on the ground strength and the vehicles, often 250–450 mm of crushed stone on geotextile for soft ground and loaded trucks. A temporary works designer should confirm it.

How wide should a site access road be?

About 3.5–4 m for one lane with passing bays, or 6–7 m for two-way traffic, plus space for pedestrians separated by barriers.

Why use geotextile?

It keeps the stone separate from soft soil, so the stone does not sink and the road lasts longer with less material.