Excavation volume = length × width × depth for vertical sides. A trench 10 m long, 1 m wide and 1.5 m deep is 15 m³ in the ground; common earth swells about 25% when dug, so you haul 18.75 m³: 2 loads in a 10 m³ truck. Sloped sides use the prismoidal formula.
My Construction Calculator
Excavation Calculator
Inputs
Results update as you type.
Quick Start
Diagram updates as you type.
Results
Check the working before you order.
Excavation (bank volume)
15.00m³
Loose volume to haul
18.75 m³
Truck loads
2 loads
Top of excavation
10.00 × 1.00 m
Price This optional: add your own prices
Your prices are remembered on this device only.
Send Order WhatsApp, SMS or email to your supplier
Bank volume = L × W × D = 10.00 × 1.00 × 1.50 = 15.00 m³
Loose volume = 15.00 × (1 + 25%) = 18.75 m³
Truck loads = ⌈18.75 ÷ 10.0⌉ = 2
Scan to open this calculationThe code links to this calculator with your inputs, so anyone can scan it with a phone camera and see the same result. Save it for a report, a site board or WhatsApp.Test copy: this code opens the live site, myconstructioncalculator.com, so it works on a phone once the site is launched.
Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.
Scan to open this calculation with the same inputs.
Generated with myconstructioncalculator.com. Estimates for planning and ordering only; verify against drawings and specifications.
Formulas
Vertical sides: V = L × W × DSloped sides: V = D/6 × (A_bottom + 4 × A_mid + A_top) top length = L + 2 × slope × D (same for width)Loose volume = V × (1 + swell %)Truck loads = ⌈ Loose volume ÷ truck capacity ⌉
Slope is horizontal distance per 1 vertical (1:1 = 45°).
Worked Examples
Trench with vertical sides: 10 m × 1 m × 1.5 m deep, common earth, 10 m³ trucks.
Bank volume = 10 × 1 × 1.5 = 15.00 m³
Loose volume = 15.00 × 1.25 = 18.75 m³
Truck loads = ⌈18.75 ÷ 10⌉ = 2 loads
Pit with 1:1 sloped sides: 2 × 2 m at the bottom, 1 m deep.
Top = 4 × 4 m (16 m²), mid-depth = 3 × 3 m (9 m²), bottom = 4 m²
V = 1/6 × (4 + 4 × 9 + 16) = 9.33 m³, more than double the 4 m³ of a vertical-sided pit
Typical Swell of Excavated Soils
Material
Swell (bank → loose)
10 m³ in the ground becomes
Sand / gravel
10–15%
11.0–11.5 m³
Common earth
20–30%
12–13 m³
Clay
30–40%
13–14 m³
Blasted rock
50–65%
15–16.5 m³
These are typical planning values; your geotechnical report or earthworks contractor will have site-specific figures.
Assumptions
Rectangular excavation with the same slope on all four sides.
Volumes are bank (in-situ) unless labelled loose. Compacted backfill shrinks below bank volume.
Safety: excavations deeper than about 1.2–1.5 m need shoring, battering or a trench box under most regulations.
Frequently Asked Questions
How do I calculate excavation volume?
For vertical sides, multiply length × width × depth. For sloped sides, use the prismoidal formula V = D/6 × (A_bottom + 4 × A_mid + A_top), where each A is the plan area at that level.
What is swell factor in excavation?
Soil takes up more space after it is dug because it loosens. Bank (in-place) volume × (1 + swell %) gives the loose volume you load into trucks. Typical swell is 10–15% for sand, about 25% for common earth, 30–40% for clay and 50% or more for blasted rock.
How many truck loads will I need?
Divide the loose volume by the truck's heaped capacity and round up. A 15 m³ excavation in common earth is 18.75 m³ loose, or 2 loads in a 10 m³ truck.
What side slope should I use?
It depends on the soil, depth, water and your local safety rules. As a guide, stiff clay may stand at ¼:1 to ½:1, average soils at 1:1 and loose sand or gravel at 1½:1. Deep excavations need a temporary works design.