Backfill Quantity Calculator

Compacted backfill = excavation − structures. To fill 90 m³ compacted you need 90 ÷ (1 − 10% shrinkage) = 100 m³ of soil as it lies in the ground, which is 125 m³ loose in trucks (25% swell) and weighs about 180 t.

Free Account Required

Sign up free with your email or Google to use this calculator. It takes under a minute and unlocks every calculator on the site.

Behind this panel: an example with the default sizes.

Inputs

Results update as you type.

Volumes
m³
m³
Fill material
kg/m³
m³
Backfill volumesBackfill volumesCompacted backfill90.0 m³Bank volume needed100.0 m³Loose volume to haul125.0 m³myconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Compacted backfill
90.0m³
Bank volume needed100.0 m³
Loose volume to haul125.0 m³
Weight of fill180.0 t
Truck loads13 loads
Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Compacted backfill = 120.0 − 30.0 = 90.0 m³
  2. Bank volume = compacted ÷ (1 − 10%) = 100.0 m³
  3. Loose volume = bank × (1 + 25%) = 125.0 m³
  4. Weight = bank × density = 180.0 t; loads = ⌈125.0 ÷ 10.0⌉ = 13

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formulas

Compacted   = excavation − structures
Bank        = compacted ÷ (1 − shrinkage %)
Loose       = bank × (1 + swell %)
Weight      = bank × bank density

Worked Example

Excavation 120 m³, structures 30 m³, common earth (25% swell, 10% shrinkage, 1,800 kg/m³):

  1. Compacted = 120 − 30 = 90 m³
  2. Bank = 90 ÷ 0.90 = 100 m³
  3. Loose = 100 × 1.25 = 125 m³ → 13 loads at 10 m³
  4. Weight = 100 × 1,800 = 180 t

Typical Swell and Shrinkage

Material Swell (bank → loose) Shrinkage (bank → compacted)
Sand / gravel 10–15% 5–10%
Common earth 20–30% 10–15%
Clay 30–40% 10–20%
Rock fill 50–65% bulks 20–30% instead

Use test results from your site where you have them.

Bags of Soil per Cubic Yard

Bag size Bags per cubic yard
0.75 ft³ 36
1 ft³ 27
1.5 ft³ 18
2 ft³ 14
40 L 20
50 L 16

Frequently Asked Questions

How do I calculate backfill quantity?

Take the excavation volume and subtract everything built inside it below ground: footings, walls, pipes, tanks, blinding. The rest is the compacted backfill volume.

What is the difference between bank, loose and compacted volume?

Bank is soil as it lies in the ground. Loose is the same soil after digging (bigger, because it swells). Compacted is the volume after rolling (usually smaller than bank, because it shrinks).

How much extra fill should I order?

Divide the compacted volume by (1 − shrinkage) to get bank volume, then multiply by (1 + swell) for the loose volume you buy or haul. For common earth that is about 1.4 × the compacted volume.

How many bags of soil are in a cubic yard?

A cubic yard is 27 ft³ (765 L), so 27 bags of 1 ft³, 18 bags of 1.5 ft³, about 14 bags of 2 ft³, 36 bags of 0.75 ft³ or 20 bags of 40 L.

How do I calculate cubic yards of dirt?

Multiply length × width × depth in feet and divide by 27. An area 20 × 10 ft filled 6 in (0.5 ft) deep is 100 ft³ ÷ 27 = 3.7 yd³. Order extra for settling if the soil will be compacted.

All Excavation & Paving Calculators