Foundation Excavation Calculator

Foundation excavation = each footing size plus working space on every side, × depth, added up for all pads and strips. Eight 1.5 × 1.5 m pads and 40 m of 0.6 m strip footing, dug 1.2 m deep with 300 mm working space, is 42.3 + 57.6 = 99.9 m³, about 13 loads of spoil.

Inputs

Results update as you type.

Pad footings
m
m
Strip footings
m
m
Excavation
m
mm
Haulage
m³
Total 99.94 m³Total 99.94 m³Pads (8)42.34 m³Strip footings57.60 m³myconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Foundation excavation (bank)
99.94m³
Pads (8)42.34 m³
Strip footings57.60 m³
Loose volume to haul124.92 m³
Truck loads13 loads

Where pads and strips meet, the overlap is counted twice: deduct it if it is large.

Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Pad dig = (1.50 + 2 × 0.30) × (1.50 + 2 × 0.30) × 1.20 × 8 = 42.34
  2. Strip dig = 40.00 × section (0.60 + 2 × 0.30 wide, 1.20 deep) = 57.60
  3. Total = 99.94 m³
  4. Loose = 99.94 × (1 + 25%) = 124.92 m³; loads = ⌈124.92 ÷ 10.0⌉ = 13

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formulas

Pad dig    = (L + 2s) × (W + 2s) × D × n       (prismoidal if sides slope)
Strip dig  = length × (b + 2s) × D             (trapezoid section if sides slope)
Total      = pads + strips

s = working space each side, D = depth to the bottom of blinding.

Worked example

Eight pads 1.5 × 1.5 m and 40 m of strip footing 0.6 m wide, 1.2 m deep, 300 mm working space, vertical sides:

  1. Pads = 2.1 × 2.1 × 1.2 × 8 = 42.34 m³
  2. Strips = 40 × 1.2 × 1.2 = 57.60 m³
  3. Total = 99.94 m³ → loose 124.9 m³ → 13 loads at 10 m³

Assumptions

  • All pads the same size; for mixed sizes, run the calculator per size and add.
  • Depth is from existing ground; any reduced-level dig over the whole site is extra: see bulk excavation.

Frequently Asked Questions

How do I calculate excavation for foundations?

Add the working space to each side of every footing, multiply by the depth to the bottom of the blinding, and add up all the footings. Strip footings are length × (width + 2 × working space) × depth.

How much working space is needed around footings?

Typically 300–600 mm each side for formwork and access. Earth-formed footings cast directly against the soil need none.

Do I count the overlap where pads and strips meet?

The calculator adds them separately, so a small overlap is counted twice. Deduct it if your layout has many large junctions.